How to Calculate the Overall Equipment/Machine Efficiency (OEE) of Garments Industries
Joyankar Mojumder
Inspector
Modern Testing Services (BD) Ltd.
280, East Narshinghpur, Ashulia, Savar, Dhaka.
Email: mozumderjoy@yahoo.com
Joyankar Mojumder
Inspector
Modern Testing Services (BD) Ltd.
280, East Narshinghpur, Ashulia, Savar, Dhaka.
Email: mozumderjoy@yahoo.com
What is Overall Equipment/Machine Efficiency (OEE):
OEE is the framework for measure the efficiency in addition to effectiveness of a process, yesteryear breaking it downwards into 3 constituent components (Availability, Performance in addition to Quality production rate). It helps to stair out a employment in addition to hence that easily tin produce it in addition to provides a standardized method of benchmarking progress. OEE identifies the percent of planned production fourth dimension that is real productive.
OEE= Availability X Performance Rate X Quality Product Rate
Where,
Loading fourth dimension – Down time
Availability = ………………………………………. X 100
Loading fourth dimension
Standard bike fourth dimension x Processing quantity
Performance = …………………………………………………. x 100
Operating fourth dimension
Processing quantity – Defective quantity
Quality production charge per unit of measurement = ……………………………………………………………. X 100
Processing quantity
Let,
- Working hours per day: x hours x threescore 2nd = 600 2nd
- Shut downwards (SD): 35 2nd
- Loading time: (600-35) = 565 2nd
- Equipment stoppage/ downwards time: (30+20+25) = 75
(b) Set upwards : 20 2nd
(c) Adjustment : 25 2nd
- Operating fourth dimension : (565 - 75) = 490 2nd
- Standard Cycle fourth dimension : 0.35 min/ pieces
- Processing quantity : 550 pieces/ twenty-four hr menstruum
- Defective : xxx pieces.
Loading fourth dimension – Down time
Availability = ……………………………………………. X 100
Loading fourth dimension
565 – 75
= ………………….. x 100
565
= 86.72%
Standard bike fourth dimension x Processing quantity
Performance = ………………………………………………….. x 100
Operating fourth dimension
0.35 x 550
= ……………………. X 100
490
= 40.35%
Processing quantity – Defective quantity
Quality production charge per unit of measurement = ……………………………………………………………………. X 100
Processing quantity
550 – 30
= …………….. x 100
550
= 94.54%
So, OEE = Availability X Performance Rate X Quality Product Rate
= 0.8672 X 0.4035 X 0.9454
= 33.08%
Low Machine efficiency charge per unit of measurement due to man:
- Management Losses;
- Motion Losses;
- Adjustment Losses;
- Losses resulting from lack of automation and
- Monitoring Losses